COMPLETION EST LATE 2026

CONSTRUCTION COMMENCED

Rectangle 91 (13)

OCTOBER 2024

The eastern side of the site has now had the 1st floor slab installed with concrete poured to a majority of it. The structure will now continue rapidly upwards.

The western side of the site is seeing the removal of existing infrastructure by Western Power, which will allow piling to be completed and work to focus on the ground floor prior to the end of the year.

AUGUST 2024

Construction at Garden Towers has moved into the footings and ground floor structure component, with piling complete to the majority of the site.

Over the next few months this part of the building will continue above ground as the podium and above ground carparks come to life.

APRIL 2024

Construction commenced!

Stay tuned for updates